CompTIA Project+ Practice Exam 1 PK0-003 CompTIA Project+ Practice Exam 1 PK0-003 There is a conflict in a project team that has no impact on the project. Which of the best conflict resolution technique? a. Confront b. Disciplinary hearing c. Avoiding d. Compromising A new inexperienced team member is not performing you should a. Train the team member b. Its not a good fit transfer her to a different project c. Encourage the newbie d. Ask other members to put in overtime to make up for it What does RTP represent a. Review for Project b. Request for Project c. Review of Formal Proposal d. Request for Proposal Why formal project closure is is important? a. Releases team members from the project b. Transfers team members to other projects c. Releases excess funding d. All of the above _________________happens in the planning phase of a project. a. Assignment and explanation of tasks b. Execution of project kick off c. Both d. Neither The part of the project charter that deals with limitations is the high level a. Risk b. Estimate c. Assumptions d. Constraints During which process groups is the availability of resources for the project determined? a. Controlling b. Planning c. Executing d. Avoiding This estimating type needs the most effort when creating WBS? a. Expert judgment b. Top-down c. Bottom-up d. Top – bottom A team member was re-assigned. The project manager should a. Replace him/her b. Advise the sponsor c. Request funding to pay overtime d. Assess how the project would be impacted In which process groups is the project charter established? a. Pre-project setup b. Post-project setup c. Project execution d. Project exiting Loading … Question 1 of 10